After initial works by sub-contractor M. Nabi and Son’s on the Guyana Football Federation’s (GFF) National Training Center’s venue at Providence on the East Bank of Demerara had commenced with the site being cleared and landfill for foundation works in October last year, it was noted that the project’s first phase would’ve been completed by January 2018.
However, during a press brief at the Providence site yesterday, head of the GFF, Wayne Forde along with the Project Manager, Rawlston Adams, noted that the revised date of completion of phase one of the project has been pushed backed until April month end.
Adams, who is on the executive committee of the GFF, explained that, “The unfavourable weather has majorly affected the project’s first phase completion and so far, the sand filling is about 60% completed. The weather we have experienced throughout the Christmas season is unlike what we have seen in a long time in Guyana.”
Phase one of the project was initially set to consist of the pitch being laid with an artificial turf, lights, goal posts and everything needed for a playable facility. However, Forde stated that the facility is set to have a higher quality Tier 2 lighting system rather than the initial plan to install Tier 3 lights.
Upon completion of all the phases, the training center will be Guyana’s first and major state-of-the-art football facility, which will seek to produce consistent levels of competitive football regionally and internationally. The facility will cater for football development among both males and females and will be the focal point for the sport at all levels of the game.
Subscribe to get the latest posts sent to your email.

Sep 24, 2026
By Samuel Whyte (Kaieteur News) – In an exciting final encounter Vryman’s Erven Secondary school defeated New Amsterdam Multilateral Secondary School to take top honours in the NA Inter...Sep 24, 2026
(Kaieteur News) – Christopher Ram is right to demand accountability for the spending of public money. He is also right that figures are most useful when they tell a coherent story about what Government has spent, what it has achieved and what remains to be done. But to ask for all of these...Sep 20, 2026
By Sir Ronald Sanders (Kaieteur News) – Crime in Latin America and the Caribbean is no longer only a matter for the police. It is weakening societies, draining economies and obstructing development. It is also testing public confidence in courts, governments and democratic institutions. The...Sep 24, 2026
(Kaieteur News) – In his 201st Oil and Gas column, the tireless Chris Ram, man of law and man of numbers, introduced a thought-provoking element in Guyana’s oil weaknesses and struggles. It’s one with explosive potential. One, if acted upon, that is sure to trigger some huge ripples...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com