Jan 09, 2020 News
The Ministry of Public Health committed a “red flag” act, after the agency extended the contract for the upgrade of the Diamond Diagnostic Centre without the approval of the tender administration board.
The contract was awarded in the sum of $21.480 million on October 11, 2016 and signed on October 17, 2016. The duration of the project was expected to last three months and therefore, the works were expected to be completed on January17, 2017.
However on January 30, 2017, the Health Ministry and the contractor signed an Addendum for additional works valued at $18.293M, which increased the contract sum to $39.773 million.
The Auditor General (AG), Deodat Persaud, in this 2018 report was keen to note that at the time of his reporting in September 2019, still no approval was granted from the National Procurement and Tender Administration Board (NPTAB) to increase the contract sum or vary the contract.
It is clearly stated in the Procurement Act of 2002 that “… procurement referred to in subsection two where and to the extent to the procurement entity, is subject to the approval of the National Board.
Each supplier or contractor is permitted to give only one price for quotation and is not permitted to change the quotation. No negotiations shall take place between the procuring entity and a supplier and contractor with respect to a quotation submitted by the supplier or contractor.”
While evidence was seen where the Health Ministry wrote to NPTAB on the December 4, 2017 requesting approval for the additional works, no approval was seen at the time of reporting.
The Ministry of Public Health had already processed Ministry’s payments totaling $38.256 million.
According to the Health Ministry’s response, the Head of Budget Agency indicated that (a) the project at the time was 98% completed.
The said works were delayed due to the sourcing of specialised flooring material from the United Kingdom (UK), for the isolation room; and a letter was sent to NPTAB on 25 January 2018 requesting approval to extend the current contract from ($18.293M) to ($39,773M).
“The Ministry is awaiting approval and final valuation,” they added.
The Auditor General recommended that the Head of Budget Agency desist from making payments for additional works without the approval of the requisite Tender Board and provide for audit examination copies of the signed contract, advance payment and performance bonds, details of the additional works and the final valuation certificate.
Subscribe to get the latest posts sent to your email.
Rising Debt, Rising US Dollar Rate in Oil-rich Guyana!

Aug 08, 2026
Kaieteur Sports – The stage is set for the National Round of 8 Playoffs of the Beharry Group of Companies Schools U-19 T-20 Tournament, as eight schools do battle in this final round of action....Aug 08, 2026
(Kaieteur News) – Political protests and theatrics go hand in hand in Guyana. A small group gathers, placards are produced, faces are arranged into expressions of grave national concern, and someone discovers that a loud voice is a useful substitute for an argument. The cameras arrive. The...Aug 02, 2026
By Sir Ronald Sanders (Kaieteur News) – Daniel Ortega has now said openly what his regime has demonstrated for years: the people of Nicaragua are not to be permitted to remove their rulers through elections. During celebrations marking the 47th anniversary of the Sandinista Revolution, Ortega...Aug 08, 2026
Hard Truths by GHK Lall (Kaieteur News) – First, the disclosures. This is owed to all Guyanese, none more than the departed in the star-crossed MV Barima. Next in line are the tragedy struck family members; parents, spouses, children, above all. Last in line in this first leadership...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com