Work on the roundabout at Vlissengen Road and Carifesta Avenue is quickly progressing and is about 15 percent complete.
The construction, which began last Tuesday, should be concluded before the scheduled six months, providing the weather permits.
Senior Engineer of the project, Sherod Parkinson, told the Department of Public Information (DPI) that works are being executed in three major sections.
“These are the filter lanes from Vlissengen Road to Carifesta Avenue; filter lanes from Carifesta to the seawall and they’ll also commence work on the filter lanes from Kitty Public Road to Vlissengen Road shortly.”
The plan is to construct all of the exterior lanes, then the centre of the intersection with minimum disruption to traffic. Parkinson explained that the design of the roundabout is very basic and similar to others found around the world.
He explained that in addition to improving traffic flow, it will allow large vehicles to traverse in and out of the roundabout with ease.
“The designs that we have to date, includes two traffic signals which will be controlling the traffic flowing in from the two major lanes, Irving Street and Kitty Public Road. Those are the two that will be monitored or controlled by traffic signals, the others will be allowed to go in and out of the roundabout without traffic signals,” the senior engineer said.
In the last phase of the project, construction will commence on the centre of the intersection. During this period, traffic will be diverted into the lanes that would have been completed. Parkinson stressed that the aim is to have the flow of vehicles run simultaneously with the works, so that drivers will not be greatly discomforted.
Earlier in the year, a $78.9M contract was awarded to S. Jagmohan Hardware Supplies and Construction Services for work on the roundabout. Engineer Johnny Raghubir, while updating DPI on the road-building aspect said “we are currently building the bypass road, we’ve finished most of the excavation and we’re doing sand filling. We have to put crusher run, loam and asphalt next, to build the road around the bypass.”
When completed, the flow of traffic in the area is expected to significantly improve.
Subscribe to get the latest posts sent to your email.
Nov 08, 2026
(Kaieteur News) – Santa Rosa Secondary and defending champions Chase’s Academic Foundation sit primed on seven points as action continues today in the Republic Bank Secondary School Football...Nov 08, 2026
(Kaieteur News) – Georgetown has become so dysfunctional, so hopelessly disorganised and so resistant to correction that one must ask whether the effort to save it is worth the trouble. The greatest mistake successive governments have made is not recognising that Georgetown should have long been...Nov 01, 2026
By Sir Ronald Sanders (Kaieteur News) – When Commonwealth leaders gather in Antigua and Barbuda from 1st to 4th November, they should address a question that reaches beyond their association: how can countries of different size, wealth and outlook sustain cooperation in a world increasingly...Nov 08, 2026
(Kaieteur News) – Another Guyanese dead, and in degraded fashion, at the hands of State agents. A State that now stands as a monument to how much the PPP Govt. has criminalized it. When not one alleged rogue cop, with blood in his eye, but four of them, can deliver blows on a man that’s...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com