Latest update April 9th, 2026 12:59 AM
Jan 05, 2017 News

A section of the runway that was under construction back in July, 2016 with vibrofloation mechanisms in the background. (File Photo)
The US$150M Cheddi Jagan International Airport (CJIA) is currently on track for its December 2017 conclusion, the Chief Executive Officer (CEO) of the Corporation, Ramesh Ghir, said yesterday.
The project was signed on November 11, 2011 between the Government of Guyana and China Harbour Engineering Company Limited (CHECL). The project is being funded through the EXIM Bank of China which initially announced that it was providing US$138M.
The Government of Guyana procured the services of engineering consultants – the MMM Group and CEMCO Inc. – taking the total cost of the project to US$150M.
The Project commenced on January 16, 2013 and works were expected to last for 32 months making the initial completion date September 16, 2015. However, due to several delays, the date was extended to December 1, 2017.
Thus far, US$75.6 million has been paid to the contractor with US$71.3 million coming from the Export-Import (Exim) Bank and US$4.4 million coming from local funding.
The cost to supervise the project was announced at US$ 5,973,752. The amount paid to date; the CEO revealed, is some US$4 million.
The runway
The runway extension – one component of the project – during the initial design, had catered for one end of the runway to be extended. However; this design was amended after the contractor encountered difficulties with the terrain. It was decided that both ends of the runway be extended by 710 metres to the north-east and 840 meters to the south-west. The initial measurement of the runway was 2270 metres (m).
Ghir reported that at the end of 2016, more than half of the total runway works were completed and the component is scheduled to be fully completed by June of this year.
Meanwhile, excavation works, and foundation treatment were fully completed with the sand backfilling process currently at 78.5 percent.
Terminal buildings
The construction of the new Arrivals Terminal Building was revealed in July this year following a visit to the CJIA by the Public Infrastructure Minister, David Patterson and his team from the Ministry.
Works on the foundation of this building is 80 percent complete and the building is scheduled to be fully completed by May this year.
The existing terminal building will be renovated to accommodate departures only. This process is set to commence next month Ghir said and will be completed by December.
The construction of a new diesel generator room; construction of a new fire pump station; the implementation of a new boarding corridor with boarding bridges were also a part of the project.
Thus far, civil works to the new generator and fire pump station is 65 percent complete with the completion date slated for March, Ghir said.
At the end of last year also, Ghir stated that Chinese labour stood at 151 and Guyanese labour, 271. It is projected that over 500 Guyanese nationals will be employed before completion of the project.
Subscribe to get the latest posts sent to your email.
Your children are starving, and you giving away their food to an already fat pussycat.
Apr 09, 2026
…Santa Rosa, St John’s, East R/veldt among winners as Massy U18 School Football continues Kaieteur Sports – Round two of the 12th Annual Massy Distribution Schools Under-18 Football...Apr 09, 2026
Kaieteur News – The rollout of the cash grant initiative was supposed to signal efficiency, modernisation, and a government in step with the digital age. Instead, what many Guyanese are experiencing is frustration, delay, and a growing sense that the system simply is not working as it should....Apr 05, 2026
By Sir Ronald Sanders (Kaieteur News) – The Caribbean has not set out to loosen its trade dependence on the United States. It is being driven to do so. For generations, Caribbean importers and consumers have looked first to the American market. They have done so for reasons of preference and...Apr 09, 2026
Kaieteur News – The headline fairly screamed: “Guyana secretly paid US$80M to Wales gas plant contractor after losing arbitration (KN April, 3, 2026). I wanted to scream. The arbitrator within counseled: go ahead, write. Excellency Ali insists that his government has been about...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com