Works on the East Coast Demerara Road Widening and Improvement Project are moving ahead and the Ministry of Public Infrastructure (MOPI) remains optimistic in meeting key milestones. The multi-million-dollar venture, which began in the latter part of last year, is approximately 13 percent complete. Works are currently ongoing in the vicinity of Better Hope and Beterverwagting.
Nigel Erskine, the Manager for Technical Services, of the Ministry of the Public Infrastructure, explained that the contractor, China Railway First Group Company Limited, has already established a concrete batching plant and will be producing concrete exclusively for the project by mid-March.
The asphalt plant has also arrived in Guyana and is being set up. It is expected that by mid-April, the contractor will be able to produce asphaltic concrete exclusively for the project.
Approximately 1.2 kilometres of lower base course has been constructed to date. A total of 3.22 kilometres has been prepared by top-soil stripping and sub-base construction.
Physical quantities executed so far include excavation of 13,555 cubic meters overburden and soft soil, placement of 15,120 cubic meters of white sand fill, placement of 3,622 cubic meters of the Lower base, and placement of 286 cubic meters of aggregate base.
According to Erskine, 3.46 kilometres of drains has been prepared for heightening on both sides of the existing carriageway. Concrete has been placed in 683 metres of these prepared lengths.
A total of 456 meters of new concrete drains have been constructed.
The relocation of utilities by the Guyana Telephone and Telegraph (GTT), Guyana Power and Light Incorporated (GPL), and Guyana Water Incorporated (GWI) is also ongoing, Erskine stated.
“The major concern is the pace with which the relocation works are progressing and to address this Minister Patterson held meetings with the utility companies, and they have given assurance that they will complete relocation on schedule,” Erskine explained.
The project focuses on the widening of the roadway into four lanes between Better Hope and Annandale, thereafter, an Asphaltic Concrete surface upgrade to Belfield. Two bridges will be reconstructed, 11 traffic light signals will be installed along the busy intersections, along with street lights, road safety signs and other speed reduction devices will be installed along the roadway.
Erskine explained, “The plan that we are working with is to have the concrete drains completed and then complete the sub-base, base and surface works. We anticipate that by mid-April, the first 2.3 km will be completed.” (DPI)
.
Subscribe to get the latest posts sent to your email.
Your children are starving, and you giving away their food to an already fat pussycat.
Jun 07, 2026
Georgetown, Guyana – Organizers of the Need for Speed Karting Championship have announced a change of venue for the opening round of the competition, which was originally scheduled to be held at...Jun 07, 2026
(Kaieteur News) – Back in 2009, legislation was passed by the then PPP/C government giving former presidents a wide range of benefits and facilities. These included security, vehicles, staff, utilities, medical expenses and other support, many of which were not subject to clear limits. Critics...Jun 07, 2026
By Sir Ronald Sanders (Kaieteur News) – Antigua and Barbuda is one of the smaller countries of the Caribbean. Yet small states have often advanced ideas that have significance beyond their size. The decision by the Government of Antigua and Barbuda, led by Prime Minister Gaston Browne, to make...Jun 07, 2026
Hard Truths by GHK Lall (Kaieteur News) – What’s up, doc? Yeah, that’s the sad reflection of the state of the Guyana presidency. Dwindled to a cartoon. If it’s not shoveling snow, it’s shoveling that other four-letter word that stinks up the environment. The great office of...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com