(Kaieteur News) – A major infrastructure push is underway in Region Two, as 23 contractors have submitted bids to execute the planned northern extension and general upgrade of the Supenaam Ferry Stelling — a project estimated to cost just over $521 million.
According to information from the National Procurement and Tender Administration Board (NPTAB), the project falls under the Ministry of Public Works and carries an estimated price tag of $521,030,974.
The 23 contractors and their respective bids are as follows:
Correia & Correia Limited who bid $532,218,358;
B.K International Inc. – $502,811,504;
Mahase Construction – $428,652,796;
MJ’s Contracting & General Supplies – $475,582,303;
LongReach Investments & Construction Inc. – $335,078,529;
DCSN Construction & General Supplies Inc. – $489,824,358;
Basheir & Son’s Construction Inc. – $476,070,261;
S. Maraj Contracting Services – $399,751,903;
D. Chowkai & Sons Construction – $483,658,403;
A&S General Contractors Inc – $474,068,518;
R&N Construction Services – $468,175,518;
Crown Road & Drainage Contractors – $416,300,612;
Mohamed’s Excavating Construction Inc. – $471,639,011.
Holistic Contracting & Procurement Inc. – $490,376,027;
B.M Property Investments Inc. – $489,514,025;
Ivor Allen – $473,901,882;
Parijan Construction – $413,300,612;
V.S Engineering & Investment – $445,212,104;
Platinum Investments Inc. – $472,420,699;
Premaul Khiemraj Construction Service – $389,597,602;
Urban Edge Builders Inc – $589,524,161;
Blue Print Builders Inc. – $581,620,161; and STP Investment Inc. – $561,300,355.
The lowest bid was submitted by LongReach Investments & Construction Inc. at $335,078,529 — nearly $186 million below the project estimate — while Urban Edge Builders Inc. submitted the highest bid at $589,524,161, exceeding the estimate by approximately $68 million.
Minister of Public Works, Juan Edghill, made the case for the investment earlier this year during the consideration of the 2026 budget estimates, painting a picture of a facility straining under the weight of its own success.
“Supenaam is becoming a hot spot and the people of Essequibo are very pleased with the level of connectivity being enjoyed, however, the facilities are aging and need upgrading,” Minister Edghill stated.
He outlined the scope of the planned works, which include repairing the catwalk and expanding the northern section of the ferry docking terminal, in addition to a comprehensive general upgrade of the facility.
“We have to get the catwalk fixed…We want to expand the northern section of the ferry docking terminal and the general upgrade at Supenaam,” the Minister said.
The project forms part of a broader government commitment to river transport infrastructure. In the 2026 national budget, the government allocated a substantial $11.2 billion for river transport — a clear signal of its intent to modernise and expand Guyana’s waterway connectivity as the country’s economy continues its rapid expansion.
Subscribe to get the latest posts sent to your email.
Rising Debt, Rising US Dollar Rate in Oil-rich Guyana!
Aug 01, 2026
(CWI) – On what would have been the 90th birthday of arguably cricket’s greatest player, Sir Garfield Sobers, the West Indies produced a memorable performance as Jayden Seales and Justin...Aug 01, 2026
(Kaieteur News) – There is a strange argument now circulating in relation to the three men charged with murder arising from the sinking of the M.V. Barima. It is being contended that because a Commission of Inquiry is about to begin its work, the criminal proceedings should not, or perhaps...Jul 19, 2026
By Sir Ronald Sanders (Kaieteur News) – Few issues test the sovereignty of small states more severely than requests made by powerful friends. How should a country respond when cooperation is expected, but the proposed terms exceed its legal, financial and institutional capacity? That question...Jul 30, 2026
Hard Truths by GHK Lall (Kaieteur News) – A tragedy of catastrophic proportions is now Guyana’s to manage. An old passenger ferry boat went to the bottom. According to news reports of Saturday, 73 bodies have been recovered and 76 rescued. Taking the official count of 179 passengers on...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com