(Kaieteur News) – The Amerindian communities of Moraikobai in Region Five and Orealla/ Siparuta in Region Six will soon get new potable water wells through the Guyana Water Inc. (GWI).
Bids for these projects were opened at the National Procurement and Tender Administration Board (NPTAB). The water well for Lower Moraikobai is estimated to cost $36.7 million, while the water wells for Siparuta and Orealla are estimated at $77.9 million.
Some $1.5 billion was approved for hinterland water supply under the Ministry of Public Utilities and Aviation in the 2026 national budget.During the presentation, Senior Minister with the responsibility for Finance, Dr. Ashni Singh disclosed that last year over 90 wells were completed along with improvements to water distribution systems in the hinterland communities such as Kumaka, Kato, and Aishalton.
In 2026, he noted that the government will provide water access to over 37,000 hinterland residents through key interventions such as construction of new wells and water distribution systems, and deploying solar PV systems to enhance reliability and reduce operating cost.
“Procure and install electromechanical components and critical spares to ensure operational reliability and long-term sustainability of existing systems. Procure and install water treatment systems to address high iron content and salinity across hinterland townships and villages,” he explained.
During the reading of tenders several GWI projects were opened for Regions Seven and Eight.
Below are the companies and their bids:
Guyana Water Inc.
Drilling of Potable Water Well in Lower Moraikobai, Region Five.
| Bidder | Amount Tendered |
| Alvin Chowramootoo Construction Services | $35,900,000 |
| K. Kissoon Contracting Service | $45,140,000 |
| Monarch Investment | $35,570,000 |
| Marvin’s Contracting Services | – |
| Manohar Service | $36,802,000 |
| Supreme Construction and Transportation | $34,589,000 |
| C. Jorree Farming & Construction Services | $33,344,000 |
| Expert Builders & Supplies Contractors | $45,130,000 |
| Double M Investments | – |
| Engineer’s Estimate | $ 36,702,000 |
Drilling of Portable Water Wells in Siparuta & Orealla Region Six.
| Bidder | Amount Tendered |
| Alvin Chowramootoo Construction Services | $76,000,000 |
| C. Jorree Farming & Construction Services | $72,688,000 |
| Supreme Construction and Transportation | $76,838,000 |
| Double M Investments | – |
| Roopan Ramotar Investment | $74,919,000 |
| Manohar Services | $77,312,000 |
| Marvin’s Contrcating Services | – |
| Adamantium Holdings | $98,780,000 |
| Karnassa Investment Incorporated | $71,830,000 |
| Expert Builders & Supplies Contrcators | $94,680,000 |
| R. Kissoon Contracting Service | $94,700,000 |
| Monarch Investments | $76,040,000 |
| Engineer’s Estimate | $77,918,000 |
Installation of Water Supply Systems in Wayaleng, Upper Mazaruni, Region Seven.
| Bidder | Amount Tendered |
| VRP Investment | $20,500,000 |
| Fazam Future Builders | $19,110,000 |
| D&R Construction and Machinery Rental | $21,156,000 |
| Andrect Engineering & Construction | $21,617,000 |
| Monarch Investments | $20,215,000 |
| Expert Builders and Supplies Contracting | $23,400,000 |
| Manohar Services | $22,056,000 |
| Ultralift (Guyana) Incorporated | $23,370,000 |
| R. Kissoon Contracting Service | $23,390,000 |
| Joshi Construction and Transportation Establishment | $21,226,000 |
| Engineer’s Estimate | $22,127,000 |
Installation of Water Supply System in Kato, Region Eight.
| Bidder | Amount Tendered |
| Hubbards Licensed Customs Brokerage & Logistics Firm | $47,920,000 |
| Andrect Engineering & Construction | $47,620,000 |
| Karnassa Investment Inc | $46,520,000 |
| D&R Construction and Machinery Rental | $48,710,000 |
| Built Right Construction Services | $42,000,000 |
| Proaxis Construction Services | $39,992,000 |
| Eco Build Development | $43,958,000 |
| Faldhari Singh and Son Contracting Services | $45,000,000 |
| C. Jorree Farming & Contracting Services | $45,080,000 |
| Nk Engineering Services | $49,550,000 |
| N and A Construction | $46,130,000 |
| Joshi Construction and Transportation Establishment Three | $47,350,000 |
| Alvin Chowramootoo Construction Services | $49,800,000 |
| Monarch Investments | $49,700,000 |
| R. Kissoon Contracting Service | $52,600,000 |
| Expert Builders & Supplies Contractors | $52,800,000 |
| Fazam Future Builders | $43,560,000 |
| Manohar Services | $47,250,000 |
| R&P Engineering and General Construction | $38,150,000 |
Drilling of Potable Water Well in Waramadong, Region Seven.
| Bidder | Amount Tendered |
| Monarch Investments | $34,690,000 |
| Karnassa Investment Inc | $34,811,000 |
| Expert Builders & Supplies Contractors | $49,340,000 |
| Morris Jeffrey Enterprise | $34,708,000 |
| C. Jorree Farming & Contracting Services | $32,950,000 |
| R. Kissoon Contracting Service | $49,330,000 |
| Joshi Construction and Transportation Establishment Three | $35,760,000 |
| Manohar Services | $35,936,000 |
| Engineer’s Estimate | $36,647,000 |
Installation of Water Supply Systems at School Island, Lower Mazaruni, Region Seven.
| Bidder | Amount Tendered |
| C. Jorree Farming & Contracting Services | $64,640,300 |
| North Stone Construction and General Supplies | $58,185,000 |
| R. Kissoon Contracting Service | $78,698,000 |
| Ultralift (Guyana) Incorporated | – |
| Morris Jeffrey Enterprise | $67,938,500 |
| Manohar Services | $50,806,000 |
| Expert Builders and Supplies Contracting | $78,498,000 |
| Expertedge Consultancy | $66,378,000 |
| Fazam Future Builders | $68,229,000 |
| Andrect Engineering & Construction | $66,306,500 |
| Monarch Investments | $68,964,000 |
| Karnassa Investment Incorporated | $66,631,500 |
| LGS Barnes General Building Construction & Civil Engineering | $68,209,000 |
| Engineer’s Estimate | $70,647,000 |
Installation of Water Supply Systems in Dagg Point, Lower Mazaruni, Region Seven.
| Bidder | Amount Tendered |
| RD Construction, Consultancy and Supply Services | $34,040,800 |
| Monarch Investments | $25,164,800 |
| Joshi Construction and Transportation Establishment Three | $29,392,000 |
| C. Jorree Farming & Contracting Services | $88,276,000 |
| LGS Barnes General Building Construction & Civil Engineering | $82,396,000 |
| Expert Builders & Supplies Contractors | $29,508,000 |
| Best Pic Investment Enterprise | $81,508,000 |
| R. Kissoon Contracting Service | $29,498,000 |
| Manohar Services | $36,276,000 |
| Cedar Engineering | $93,474,500 |
| Expertedge Consultancy | $87,914,000 |
| Faldhari Singh and Son Contracting Services | $27,000,000 |
| R&P Engineering and General Construction | $30,262,600 |
| Fazam Future Builders | $82,202,000 |
| Engineer’s Estimate | $34,637,000 |
Installation of Water Supply Systems in Mora Camp & Kalcoon, Lower Mazaruni, Region Seven.
| Bidder | Amount Tendered |
| Monarch Investments | $87,198,000 |
| Faldhari Singh and Son Contracting Services | $64,000,000 |
| Cedar Engineering | $63,221,000 |
| Expert Builders & Supplies Contractors | $124,684,000 |
| LGS Barns General Building Construction & Civil Engineering | $87,534,000 |
| R.Kissoon Contracting Service | $123,884,000 |
Subscribe to get the latest posts sent to your email.
Your children are starving, and you giving away their food to an already fat pussycat.
Apr 01, 2026
-Windwards beat Leewards by 30 runs, Jam/T&T match washed out Kaieteur Sports – Mother Nature again controlled the ebb and flow of competition as two of yesterday’s three games were...Apr 01, 2026
(Kaieteur News) – Fifteen years ago, a pastor was so appalled at the attire he witnessed at funerals in Barbados that he indicated to those planning to attend future funerals that it was okay for them to wear whatever they had and not be restricted in wearing black and white clothing. The same...Mar 29, 2026
By Sir Ronald Sanders (Kaieteur News) – The Organization of American States is approaching a defining test, not of its existence, but of its significance. It continues to meet, to commemorate events, but fails to tackle pressing political issues. At a time of global turmoil, economic strain, and...Apr 01, 2026
(Kaieteur News) – ‘We stand with the Guyanese people.’ Nothing could be better. If only it were so. ‘We will fight for all citizens.’ When anyone, just one, encounters such a battler, introduce me. Whether Antarctica or Guyana, politicians possess common connections. For the...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com