Nov 28, 2021 News
Despite no approval for Yellowtail…
Kaieteur News – Should the Stabroek Block partners receive the requisite government approvals for its fourth project called Yellowtail in a timely fashion, start-up is poised to commence as early as 2025. But following this, Guyana should expect to see one floating, production, storage, and offloading (FPSO) vessel being added to its offshore armada every year. This is according to Hess Corporation’s Chief Executive Officer (CEO), John Hess.

Map showing the potential areas for development in the Stabroek Block by ExxonMobil and its partners, Hess Corporation and CNOOC/NEXEN
During a recent interview, the Hess boss said the partners already have a line of sight for the first seven ships while adding that the Uaru-Mako discoveries could possibly support the fifth development on the block.
Readers would recall that the Mako-1 discovery was announced in December 2019. The well encountered approximately 164 feet (50 metres) of high-quality oil-bearing sandstone reservoir and was drilled in 5,315 feet (1,620 metres) of water.
On April 27, the company announced that it had hit pay at Uaru-2 encountering approximately 120 feet (36.7 metres) of high-quality oil-bearing reservoirs including newly identified intervals below the original Uaru-1 discovery. The well was drilled in 5,659 feet (1,725 metres) of water and is located approximately 6.8 miles (11 kilometres) south of the Uaru-1 well.
The CEO said, “A lot of our exploration and appraisal programme is going to give us further clarification on what ship six is, what ship seven is, and probably what ship eight is …But the visibility to get to those 10 ships is not a matter of if but when.” He added, “We continue to see the potential for at least six floating, production, storage and offloading vessels producing on a gross basis greater than one million barrels of oil per day by 2027.”
He said too, that as each ship comes online, the company stands to benefit at least, US$1B annually in profits from each ship. In the meantime, he said the partners are working towards approval for the Yellowtail project which is set to be Guyana’s largest oil-producing field.
It was only last month that Kaieteur News reported that development costs for the Yellowtail project are poised to exceed US$9B or GY$1.8 trillion.
ExxonMobil’s subsidiary, Esso Exploration and Production Guyana Limited (EEPGL) which is the operator of the Stabroek Block, had said costs are expected to be higher, since there would be a greater number of development wells and associated drilling costs when compared to its Payara project which will also cost Guyana $1.8 trillion.
According to project documents, Yellowtail will consist of drilling approximately 41 to 67 development wells (including production, water injection, and gas re-injection wells); installation and operation of Subsea, Umbilicals, Risers, and Flowlines equipment; installation and the operation of a Floating Production Storage and Offloading (FPSO) vessel in the eastern half of the Stabroek Block; and— ultimately—project decommissioning.
The FPSO will be designed to produce up to 250,000 barrels of oil per day. The initial production is expected to begin by the end of 2025 early 2026, with operations continuing for at least 20 years.
The project is expected to employ up to 540 persons during development well drilling, approximately 600 persons at the peak of the installation stage, and 100 to 140 persons during production operations.
Subscribe to get the latest posts sent to your email.
Jul 28, 2026
Cricinfo – The first ever Test at Tarouba made giant strides on the third day, claiming 14 wickets and hurtling towards its denouement. And yet, it appeared to stand in almost exactly the same...Jul 28, 2026
(Kaieteur News) – Parliament has never been a silent chamber. Around the world, legislatures have always been places where members interrupt, heckle, applaud loudly, exchange sharp remarks and use wit to make political points. These moments are part of parliamentary democracy. They reflect...Jul 19, 2026
By Sir Ronald Sanders (Kaieteur News) – Few issues test the sovereignty of small states more severely than requests made by powerful friends. How should a country respond when cooperation is expected, but the proposed terms exceed its legal, financial and institutional capacity? That question...Jul 27, 2026
(Kaieteur News) – There’s human devastation. Still, the PPP Govt commits to deflection. The MV Barima disaster qualifies as extreme domestic devastation. Families and communities battered. The nation bowed. Rather than strengthening citizens in a time of tribulation, the government...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com