Oct 22, 2020 News
– was given five-day deadline since August
By Shikema Dey

The renovated terminal building that Guyana got as part of the US$150M-plus project at CJIA. It was supposed to be new. (Mike Charles’ Facebook Photo)
Kaieteur News – Chinese contractor, China Harbour Engineering Company (CHEC), continues to display blatant disrespect to the governing administration as it has not yet submitted the revised work plan for the Cheddi Jagan International Airport (CJIA) US$150 million and counting renovation project after being given a five-day deadline back in August.
That deadline was granted by the Ministry of Public Works, since August 28 after a visit by President Irfaan Ali. However, when asked yesterday if the contractor met the deadline, Public Works Minister, Juan Edghill answered in the negative.
He said, “I have not seen as of now a work plan that will give us what His Excellency, President Ali, requested when he visited the airport.”
That revised work plan is expected to capture the agreed upon terms in the initial contract signed by the contractor and the People’s Progressive Party Civic (PPP/C), which was also in government back in 2011. It is also expected to outline how the long list of defects at the country’s main port of entry will be fixed and a revised deadline.
The multi-billion dollar contract has been in the hands of CHEC during the PPP/C tenure from 2011-2015. The project should have been completed in December 31, 2018 but substandard works turned what should have been a state-of-the-art airport into merely a renovated facility.
When asked about government’s next move, Minister Edghill said, “There is a continual engagement between the government and CHEC to deliver an airport that is in keeping with what we envisaged and that engagement is continuing and the contractor has been advised that, that engagement will take place at the highest level from the office of the President.”
CHEC has been under fire for the shoddy works done at the airport, on multiple occasions. In fact, government was forced to cease the heft duty-free concession handed to the company after it failed to adhere to its contractual obligations.
While the initial cost for the renovation stood at US$150 million, the governing PPP/C will still have to pump an additional US$6.5 million to ensure that the almost 10-year-old project is completed to international standards.
Notably, contention continues to grow over the cost of the airport, after in January of this year, recent invitations for bids advertised in the daily newspapers had indicated that the airport needed a new fence for its public car park and an access control security hut. These intended projects, which stand outside of the US$150 million and counting contract, are not alone.
There are also plans for a new parking lot valued at $122 million, a cargo facility, a commercial centre, an office area and a parking lot, all advertised last year.
It has been argued, however, that the projects should never have been left out in the first place, as contractors have told Kaieteur News that the amount and quality of work being done to renovate the terminal building since it began could have been done for US$5 million – 30 times less than the more than US$150 million that taxpayers are expected to foot.
Subscribe to get the latest posts sent to your email.
Rising Debt, Rising US Dollar Rate in Oil-rich Guyana!

Aug 17, 2026
Punta Cana, Dominican Republic – The Guyana Football Federation (GFF) Under-14 Boys made a commanding start to the 2026 Caribbean Football Union (CFU) U14 Challenge Series, securing a resounding 8...Aug 17, 2026
(Kaieteur News) – One of the persistent afflictions of post-colonial societies is the absence of planning commensurate with ambition. Governments announce grand projects, inaugurate grand buildings, make grand speeches and produce grand visions, but somewhere between the vision and the delivery...Aug 16, 2026
By Sir Ronald Sanders (Kaieteur News) – Haiti’s plight must not be forgotten because it is no longer a regular feature of international headlines. The suffering has not diminished. Between January and early June 2026, at least 2,310 people were killed, 1,106 were injured and 99 were kidnapped,...Aug 17, 2026
(Kaieteur News) – I have heard about a hanging judge. From readings, I know about travelling judges. There’s familiarity with governing judges better known as Administrative Law Judges. Thanks to the leader of the A Partnership for National Unity (APNU), Mr. Aubrey Norton, I now have my...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.