Work on Guyana’s first ever Solar Farm in Mabaruma, Region One (Barima-Waini) has begun.
The construction of the $264M mega solar farm is being executed in three phases.
The first phase will see the extension of the distribution network from its endpoint to a new location in Khan’s Hill. The second stage, according to a Government statement, caters for site preparation and construction of the fence, while the third phase involves the actual construction of the solar farm.
Electrical Engineer for Region One, Frederick Cort, in updating the Department of Public Information on the project’s status, explained that “so far we’ve completed the extension of the network and the preparation of the site. We’re currently in preparation for the fence, which is expected to be completed by the end of February.”
Cort explained that inclement weather has delayed the shipping of the material to the North West district, resulting in the late start of the project. He said there have been other challenges, however, the Ministry remains focused on its objective to complete the project in a timely manner.
Currently, the Mabaruma Power Company provides an electrical supply for nine hours daily to approximately ten communities across the Mabaruma sub-district. Cort said that when completed, the solar farm will be handed over to the power company.
The solar farm is being constructed by German company Meeco and will result in over 700 residents and commercial consumers benefitting from increased hours of electricity service – from 16 hours in Phase One, initially, and eventually to 24 hours.
Other benefits include “the reduction of the fossil fuels for the generation of electricity. The solar farm should be able to power three-quarter of the community and the remaining quarter will be powered by fossil fuel or diesel which is the main usage in the Mabaruma sub-district,” the Electrical Engineer underlined.
The initiative is part of the government’s plan to move Guyana towards becoming a ‘Green State’ and will serve as a medium to reduce the country’s fossil fuel bill and prevent carbon emissions.
Other solar farms at Lethem in Region Nine (Upper Takutu-Upper Essequibo); Mahdia in Region Eight (Potaro-Siparuni) and at Bartica in Region Seven (Cuyuni-Mazaruni) will be pursued.
These farms are anticipated to generate 800, 400, and 1.5 kilowatts of electricity respectively.
Subscribe to get the latest posts sent to your email.
Rising Debt, Rising US Dollar Rate in Oil-rich Guyana!

Aug 07, 2026
By Rawle Toney (Kaieteur News) – Guyana eyes breakthrough on Day 3 in Oregon. Guyana’s pursuit of its first medal at the World Athletics U20 Championships in 14 years continues today, with...Aug 07, 2026
Peeping Tom… (Kaieteur News) – There is a peculiar tendency among many local commentators to look at a disaster and see a conspiracy before the investigators have found the wreckage. These commentators possess the rare strategic gift of knowing not merely what happened, but why it...Aug 02, 2026
By Sir Ronald Sanders (Kaieteur News) – Daniel Ortega has now said openly what his regime has demonstrated for years: the people of Nicaragua are not to be permitted to remove their rulers through elections. During celebrations marking the 47th anniversary of the Sandinista Revolution, Ortega...Aug 07, 2026
Hard Truths by GHK Lall (Kaieteur News) – Pres. Ali reminds of a wrestler who steps into the ring for a fight. He’s under pressure but has an ace. The president walks into the square circle with his own bell. One of those newfangled contraptions that come with an on-and-off switch. No...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com