GreenHeartTree Energy (GHTE) has taken the initiative to design, engineer, procure,
construct and deliver a non-grid connected solar PV micro-grid system for the Paramakatoi Flavours Sun-Dried Tomato Plant. This system takes into consideration the actual climatic data and historical weather patterns of the area.
Engineers ran multiple simulations to determine the correct system size based on battery storage capacity, solar PV capacity and the predicted electrical loads requested in the Request For Proposal (RFP) by the Institute of Applied Science and Technology (IAST).
The Paramakatoi Flavours system includes three solar PV racks or arrays complete with top grade Hanwha Q-Cell Modules and American made, German Engineered Schletter Racks. Adjacent to the solar PV arrays is a small building, shipped from Canada, designed to house the batteries and electronics.
The lead-acid batteries are on a pre-assembled custom built battery skid. Each battery comes complete with a visual monitoring float for each cell within every battery. GHTE has included in the shipment additional battery water to ensure the system is maintained using the correct materials and fluids.
The battery inverter, solar PV inverter and a Smart-Transformer will be mounted inside the building on a custom build galvanized steel frame.
AC Coupled MircoGrid System
GHTE has engineered a system that is on the leading edge of technology for microgrid systems. This is an AC coupled system unlike a typical DC coupled one. Even though they usually include an inverter, most battery-based PV systems are “DC-coupled”
AC coupled PV systems are gaining wider support through several battery-based inverter manufacturers.
GHTE pre-assembled the entire battery system on a custom built skid and electronic components on a custom steel frame to test and confirm operation prior to shipping. Testing in Canada ensures that when the system arrives in Guyana the ‘bugs’ have been worked out and reduces the installation time on site.
Once the system installation is complete engineers complete a final quality control check to ensure that all check points of the system construction have been completed to our high quality standards.
GHTE has provided technical manuals for all components used along with a technical user’s guide that outlines necessary maintenance check-points, schedules and defined user necessary operating details.
Subscribe to get the latest posts sent to your email.

Sep 22, 2026
…Hamilton, Dennis star with hat-tricks (Kaieteur News) – The goals came in bunches as Guyana Football Federation’s Season Eight Elite League produced another weekend of attacking football,...Sep 22, 2026
(Kaieteur News) – There are many things Guyana has acquired since the discovery of oil, including wealth, multi-storied buildings, newly built apartments that will remain empty, traffic jams and the sudden appearance of people who have always known how to spend money they never previously had....Sep 20, 2026
By Sir Ronald Sanders (Kaieteur News) – Crime in Latin America and the Caribbean is no longer only a matter for the police. It is weakening societies, draining economies and obstructing development. It is also testing public confidence in courts, governments and democratic institutions. The...Sep 22, 2026
(Kaieteur News) – This is the secular world. Not the space of the spiritual. It’s a world of sometimes subtle, other times, astonishing changes. The areas covered are endless. Filled with the contradictory. Where crimes are covered over (transgressions overlooked). Pursued for the...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com