The National Drainage and Irrigation Authority (NDIA) Act No. 10 of 2004 provides for the appointment of Committees to help the Board meet its obligations as outlined in the Act; however, a forensic audit into the agency has indicated that these committees failed to carry out their mandates – terms of reference.
The audit report stated that based on the Board minutes of March, 2011, two committees were appointed: The Works and Tender Committee and the Finance and Administration Committee. In March 2013 two similar committees were again appointed and reconstituted, the Finance and Administrative Committee and the Works Committee.
WORKS COMMITTEE
The report stated that according to the Board Minutes of December 14, 2011, The Works Committee visited the East Demerara Water Conservancy (EDWC) Northern Relief which at that time, was under construction at Hope/Dochfour.
The committee also visited the Greenfield pumping station and sluice and the Abary and Cottage Sluices. On December 20 and 23, 2013, the Committee met to discuss the Pineground Project and on January 27, 2015, the Works Committee met to discuss the construction of the pump station at Vriendschap and to review findings of the purchase of controversial sheet piles. The minutes were available for the Works Committee meetings held on those dates, the auditors stated.
However, outside of these activities, the report stated that the Committee scarcely addressed its terms of reference which included critical areas such as the review designs; review of bills of quantities; specifications of works to be undertaken by NDIA and to make recommendations to the Board; provide advice in relation to planning, coordination and execution of capital works; and infrastructure programme; recommend work priorities for capital projects; provide quarterly reports among many other tasks and responsibilities.
An evaluation of the terms of reference of the Works Committee against what was actually done showed that the committee failed to comply with its terms of reference.
FINANCE AND ADMINISTRATIVE COMMITTEE
The Finance and Administrative Committee – was tasked with investigating one issue at a committee meeting on December 30, 2014.
On February 13, 2015, the Chairman of the Administrative and Finance Committee provided a comprehensive report on the issue for the Board’s consideration and acceptance. No decision was taken on the recommendation up to the last Board meeting held for period under review.
Other than this assignment, the audit report stated that the Finance and Administrative Committee “never really” addressed its terms of reference which included matters critical to financial governance; including: overseeing the financial affairs of NDIA, recommend the annual budget, review the annual financial statements and make recommendations as necessary, ensure that assets are properly managed, review quarterly accounts and make recommendations, oversee the strategic planning and review accounting and auditing procedures.
The auditors stated that given the scope and importance of the role of the Finance and Administrative committee in setting sound financial governance practices, it “certainly failed” during its tenure to deliver on its mandate and its ineffectiveness contributed to the myriad problems identified in the NDIA report.
Subscribe to get the latest posts sent to your email.

Sep 09, 2026
2026 Republic Bank CPL…GAW vs. ABF – Guyana lose by 65-runs (Kaieteur News) – Guyana Amazon Warriors had their fairy-tale, unbeaten run this season come to an abrupt end, after the Antigua...Sep 09, 2026
(Kaieteur News) – Empire, in its modern form, seldom arrives wearing a military uniform. It comes dressed instead as an investment banker, carrying a development plan, or as the representative of a multinational corporation bearing gifts in the language of progress. The empire does not always...Sep 06, 2026
By Sir Ronald Sanders (Kaieteur News) – The world has broken the 1.5°C promise it made to its most vulnerable countries. The breach has not yet been recorded on a sustained basis, but the United Nations Environment Programme (UNEP) says it is widely assessed as unavoidable and likely within the...Sep 09, 2026
(Kaieteur News) – It was just a matter of when. From where they hail. Then, how many of them. Last, what kind of undesirables. They go by the name of ‘deportees’, third country nationals. From the moment the first word of a destination for deportees from the U.S. came up, I...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com