Latest update September 28th, 2026 10:20 AM
Sep 27, 2026 News
(Kaieteur News) – The National Procurement and Tender Administration Board (NPTAB) has received a number of bids from reputable companies, again interested in building a hydro-power project at the Amaila Falls in Region Eight.
President Irfaan Ali in an interview with ‘Fueledgy’ shared an update on the energy project as the country continues to suffer daily blackouts.
He said, “It’s at the evaluation stage now so as soon as that evaluation is completed I have instructed that we move to negotiate with the best ranked bidders who give us the best possibility.”
Back in May this year, five bids were opened at NPTAB for the hydropower project. It was reported that three Chinese firms submitted proposals to the government while the other two were headquartered in the United States of America and India.
Ali noted, “They have to agree to the terms, the terms that make economic sense for us and would meet the energy cost that we want to deliver to the people of this country.”
The government, in its revised Request for Proposals (RFP) which was issued earlier this year, stated that the hydro project will be done under a Build-Own-Operate-Transfer (BOOT) model, with a minimum installed capacity of 165 Mega Watt (MW).
In a summary of the scope of work, the RFP detailed that the project includes a 165 MW installed hydro dam, plant, and substation at Amaila site, and related works.
The project involves the creation of a 23 square KM storage reservoir consistent with the environmental reports and studies and prior permitting. Also interested parties would have to assume all geo-technical risks including guarantees relating to the structure of the reservoir and dam.
The government also stated that the transmission network will be built separately.
Under the BOOT arrangement, the Government of Guyana (GoG) will purchase the electricity from the private developer. As such, the RFP explained that government will select a suitable partner based on (i) lowest Power Purchase Agreement (PPA) price, Engineering, Procurement and Construction (EPC) price, operating cost and capital amortisation; (ii) timeframes to complete and (iii) ability to finance the project on a PPA basis.
Since assuming office in 2020 under the first Irfaan Ali-led PPP administration, government tendered twice for a contractor for the project but both were unsuccessful in materialising.
The Amaila Falls Hydro project was introduced by a previous PPP/C Administration in 2011. However, the project faced obstacles in its realisation when the A Partnership for National Unity (APNU) and the Alliance For Change (AFC) Opposition parties, stopped the project back in 2014.
In its 2020 election manifesto, the PPP-administration noted that the project will be revived. However, the PPP government was unable to do so before the end of the first term in office.
In 2021, negotiations hit a stalemate after Cabinet granted a no-objection for the Prime Minister’s office to engage the China Railway Group Limited for construction. Discussions faltered as the company sought to alter the project’s model due to financing challenges for a BOOT model, requesting a shift to an EPC model. The government was reluctant to switch to the EPC option, resulting in the talks with the Chinese contractor coming to an end.
The government later issued a revised RFP under the BOOT model for the Amaila Falls project and four local and international firms submitted proposals for the Amaila Falls project that was scheduled to begin in 2027. However, this too was stalled.
Early in 2025, the government announced that it would once again go to tender for the project.
Subscribe to get the latest posts sent to your email.
Sep 28, 2026
…Williams also dominates (Kaieteur News) – Guyana ended their 2026 South American Powerlifting Championships campaign with a bang on Saturday evening in Santiago, Chile when the nation’s 105kg...Sep 28, 2026
(Kaieteur News) – You can go to the doctor and get tablets for high blood pressure. You can get medication for diabetes. You can even get something to help you sleep after spending the entire night worrying about whether somebody else has more money than you. But if your neighbour buys a new...Sep 20, 2026
By Sir Ronald Sanders (Kaieteur News) – Crime in Latin America and the Caribbean is no longer only a matter for the police. It is weakening societies, draining economies and obstructing development. It is also testing public confidence in courts, governments and democratic institutions. The...Sep 28, 2026
(Kaieteur News) – Karma has its place, actually works. There is karma for even a non-Kshatriya. Not the kind touted by Mr. Carmichael Street. My own kind. It is a combination of the unfathomable will of God, the arc of justice and, believe it or not, the black cat crossing the path. I...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com