(Kaieteur News) – The Guyana National Control Centre (GNCC), a US$9 million facility being developed as part of the Wales Gas-to-Energy project, is on track to become operational by August 2026, according to the Ministry of Public Utilities and Aviation.
Minister of Public Utilities and Aviation, Deodat Indar on Tuesday led a site visit to inspect ongoing works on the construction of the GNCC – which is a critical component of Wales Gas-to-Energy (GTE).
The facility is currently going through testing of functionalities that include power, internal generators, security, water, and air conditioning systems, among a host of integral parts of the GNCC.

Minister of Public Utilities and Aviation, Deodat Indar and others during the site visit at the GNCC
During the visit, the Guyana Power and Light (GPL) Incorporated senior officials noted that the GNCC’s Supervisory Control and Data Acquisition (SCADA) equipment is in the country and is currently undergoing acceptance testing at the power company’s secondary control centre at Sophia. The SCADA equipment will enable GPL to monitor, control, and optimise electricity distribution across the Demerara–Berbice Interconnected System (DBIS), thereby significantly strengthening real-time management and improving overall system reliability.
The ministry stated that GPL anticipates the new facility will be fully operationalised by August 2026, following successful acceptance of all tests.
The Wales GTE project, which includes the construction of a Natural Gas Liquids (NGL) facility and a 300-megawatt (MW) power plant at Wales, West Bank Demerara, has faced mounting criticisms over delays and escalating costs.
The project is now expected to achieve first power by the end of 2026. The project’s initial deadline was December 2024.
While the first power turbine is expected to come online by the end of 2026, the other gas turbines are expected to be fully commissioned by the first quarter of 2027 and the combined cycle operation to be completed by June 2027.
According to reports, Power China International Group Limited out of Beijing, China was awarded a $1,827,929,605 (US$9M) contract to construct GNCC back in 2024. The GNCC is a project being executed by the Office of the Prime Minister, and it aimed at managing the affairs of the gas-fired power plant.
Subscribe to get the latest posts sent to your email.

Sep 18, 2026
2026 Republic Bank CPL… GAW vs. ABF – Falcons book spot in finals, Warriors/Kingsmen battle tonight for last spot By Clifton Ross (Kaieteur News) – Guyana Amazon Warriors choked their...Sep 18, 2026
(Kaieteur News) – There is something deeply troubling about the driver’s-licence saga in Guyana. And it is not simply the question of whether a few police officers may have done something wrong. It is the possibility that people are driving on our roads who were never properly tested, never...Sep 06, 2026
By Sir Ronald Sanders (Kaieteur News) – The world has broken the 1.5°C promise it made to its most vulnerable countries. The breach has not yet been recorded on a sustained basis, but the United Nations Environment Programme (UNEP) says it is widely assessed as unavoidable and likely within the...Sep 18, 2026
(Kaieteur News) – The Hon Speaker of the House started the ball rolling. The wrong way. Neither time nor space for opposition in parliament. For months after the September elections, the machinery of parliamentary democracy couldn’t get cranking. The white people had to intervene so...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com