Latest update September 16th, 2026 10:20 AM
Aug 21, 2025 News
Kaieteur News – After failing to deliver a 50% reduction in electricity prices with the completion of the Gas to Energy project in 2024, with its completion date being pushed back twice, the People’s Progressive Party Civic (PPP/C) is now promising a second gas project alongside the reduced rates for a second term.
In the party’s manifesto, which was launched on Monday the PPP/C said that over the next five years it will complete the Gas to Energy Project, subsequently reducing the “electricity tariffs by 50 percent to consumers on the grid. Complete the rebuild of the T&D network, and the installation of a smart grid, to offtake the additional power being produced, improve network reliability, reduce losses, and improve efficiency.”
Additionally, the party is promising a second gas-to-energy project, which it said will bring an additional 300Megawatt of power to be able to meet future demand given the country’s economic growth trajectory. In an effort to generate even more power for citizens they will also “continue efforts to resuscitate the Amaila Falls Hydropower Project (AFHP), and install an additional 100 MW of solar power, to further advance the diversification of the energy matrix.”
On August 14 Kaieteur News reported Vice President Bharrat Jagdeo saying that while he is not aware of what percentage of the Gas-to-Energy (GTE) project is completed, he knows that the deadline is still mid-2026. The GTE project, located in Wales on the West Bank of Demerara, includes a Natural Gas Liquids (NGL) facility and a 300-megawatt (MW) power plant.
Natural gas will be transported from the offshore Stabroek Blocks Liza oilfield via a 12-inch pipeline to the site, where 50 million cubic feet (MMCFD) of gas will be converted to electricity daily.
During a recent episode of Starting Point, Jagdeo noted, “I don’t know the exact percentage but we are still targeting completion by mid next year.” He said that he was informed that a lot of work had been done on the foundation and pile driving.
“The turbines came to the country, but they have been sitting for a while because of the delays in the project,” he added. Back in 2022, government hired CH4 (Texas) and Lindsayca (Puerto Rico) for the construction of the power plant and NGL facility at a cost of US$759 million. However, it was recently announced that the companies have split-up.
Government has assured that this split between the joint venture CH4 and Lindsayca would not affect the completion of the project.
Further, Jagdeo underscored the importance of the project and reiterated the government’s promise to slash electricity bills by 50% through the US$2 billion project.
Notably, the GTE project was initially slated for completion by the end of 2025. Then, in February, Head of the GTE Taskforce, Winston Brassington, said that a more realistic target would be the first half of 2026. However, a few months later, Prime Minister (Retd) Brigadier Mark Phillips estimated that the project would be completed in the second quarter of 2026.
Ahead of the completion of the Wales GTE project, the government awarded a US$422 million contract for the extension of transmission lines for the Guyana Power and Light (GPL). The transmission lines are being constructed along the eastern corridor of the Demerara-Berbice Interconnected System (DBIS). Jagdeo noted, “That project when completed in all of its form, will allow us to solve a lot of the power problems we have.”
Subscribe to get the latest posts sent to your email.

Sep 16, 2026
2026 Republic Bank CPL… – says not crossing finish line now, a waste of hard work By Clifton Ross (Kaieteur News) – The Guyana Amazon Warriors have done it again, securing yet...Sep 16, 2026
(Kaieteur News) – There is nothing wrong with warning public officials that procurement breaches will have consequences. In fact, it is long overdue that every person entrusted with public money understands that the public purse is not a personal purse. But there is a fundamental question which...Sep 06, 2026
By Sir Ronald Sanders (Kaieteur News) – The world has broken the 1.5°C promise it made to its most vulnerable countries. The breach has not yet been recorded on a sustained basis, but the United Nations Environment Programme (UNEP) says it is widely assessed as unavoidable and likely within the...Sep 16, 2026
(Kaieteur News) – Guyanese love their music. I do, too. The problem is that Guyanese love their music much too much. It’s a big problem, a national one. Citizens clash with members of the Guyana Police Force trying to do their job, establish sanity around the Kitty area. Citizens in...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com