Kaieteur News – Several measures are being implemented at the Demerara Harbour Bridge Corporation (DHBC) to facilitate maintenance work, following damage to the structural integrity of its span nine.
This is according to a Department of Public Information (DPI) report.
In that report, it was noted that Minister of Public Works, Hon. Bishop Juan Edghill, had on Sunday engaged technical staff of the DHBC and was updated on the emergency works going forward after a series of analyses were conducted.
Minister Edghill, according to the DPI report, said that remedying the situation is government’s priority since the bridge is essential to the lives of all Guyanese, especially those who traverse it daily for work or business.
He noted that “every effort is being made to ensure that we could get vehicles crossing the bridge, supplies can move from the east to the west and vice versa; people can get to work, and we can respond to medical and security emergencies.”
To this end, the Minister said that the usual number of daily retractions would be reduced.
“The bridge cannot be opening two times a day. We have already engaged the agents and owners of ocean-going vessels and we want that every time there is a retraction, there must be about five to six vessels passing. The fact that they have to slow down, it means that the retractions will take a little longer than normal. We are looking at opening and closing to allow vessels to transit at times when it’s less impacting to vehicular traffic, which will be at nights.”
It must be noted that there would not be any retraction between 2pm and 5pm, as this will help to create a smooth flow during the “rush hour” period.
In some instances, however, Minister Edghill noted that there are times the bridge will be opened during the day to facilitate tugs and barges, which are not safe to transit at nights. He said an analysis of the traffic pattern is being conducted and a schedule would be established.
The Minister also said there are plans to place traffic police at strategic points along the bridge with radar speed guns to monitor drivers’ speed, while other methods are being sought for the same strategy to be used for river traffic.
Minister of Home Affairs, Hon. Robeson Benn, has already been notified of the new approach.
“We have to get these measures in place in a matter of hours and we are working around the clock,” Minister Edghill relayed.
He pointed out that while the damage to the bridge is caused by both vehicular and marine traffic, it is caused mostly by speeding heavy trucks and the application of sudden brakes.
The Minister said consideration is also being given to ferrying heavy-duty vehicles across the river by barge, and private sector operatives have already indicated their willingness to aid in this regard. However, landing spots on both the east and west banks of the river remain a challenge.
Meanwhile, Engineer, Mr. Marcel Gaskin, explained that the bridge has outlived its lifespan and is showing signs of serious wear and tear. He said the approach to fixing the issues would be done over short and long-term phases, even as plans are streamlined to establish the new Demerara River Bridge.
Gaskin said this includes replacing the retractor span [a retractor span opens and closes to allow large vessels to pass]. Currently, span nine is worse than span 10, but both have suffered severe damage. Gaskin predicts that the situation should be fixed over a six-month period.
Highlighting some of the short-term measures, the engineer noted that the “roller cards” will be replaced. These are the underside protection, which are located at the area that opens and closes the bridge.
“We have to design and install what we call an exoframe, which is a frame to the outside of the existing bridge structure that is going to support those panels of the retractor spans that are broken. We have to procure spare static rollers and spare travelling rollers. All these are rollers that enable the bridge to open and close. We want to have spares, so in case anything happens to the existing ones, we have those in place,” Gaskin added.
Meanwhile, Minister Edghill apologized for the inconvenience caused during the traffic backup on Saturday, stating that the closure of the bridge, between 11:30 hrs. and 13:00 hrs., was to allow the pins to be fixed.
However, the one and a half hours of maintenance work did not remedy the problem at span nine. “All it did was to allow us to fix one of the 272 pins to get the bridge into some shape to allow for retractions for marine traffic and to keep vehicular traffic moving. We have had to start releasing trucks on the bridge at intervals and the fact that they are going at intervals it caused a build-up. We also have a situation where marine traffic, because some of them are moving with such speed and creating waves, they are causing the misalignment on the bridge,” the Minister said. Inspection of the bridge continues daily, according to DPI.
Feb 22, 2025
Kaieteur Sports- Slingerz FC made a bold statement at the just-concluded Guyana Energy Conference and Supply Chain Expo, held at the Marriott Hotel, by blending the worlds of professional football...Peeping Tom… Kaieteur News- Time, as the ancients knew, is a trickster. It slips through the fingers of kings and commoners... more
By Sir Ronald Sanders Ambassador to the US and the OAS, Sir Ronald Sanders Kaieteur News-Two Executive Orders issued by U.S.... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]