Dec 21, 2020 News

ExxonMobil had been flaring gas at the Liza Destiny vessel all year, despite the fact that the gas is supposed to be re-injected into the reservoir. This photo, which was taken just a few days ago, shows Exxon flaring at day.
Kaieteur News – As production at the Liza Destiny Floating Production and Offloading (FPSO) vessel reaches full capacity of 120,000 barrels of oil per day, ExxonMobil claimed that it has “successfully commissioned the gas injection system”, which was previously reported as being defective, thereby causing Exxon to flare billions of cubic feet of toxic natural gas. These and other details were shared by President of ExxonMobil Guyana, Alistair Routledge, yesterday.
“Earlier this month,” Routledge said, “we were able to reduce the flaring to its background levels, just to pilot flare levels and now we’re operating at capacity.”
Research indicates that combustion requires three ingredients: fuel, an oxidizing agent (typically oxygen in air), and heat (or ignition source). Flares typically operate with that said pilot flames to provide the ignition source, and they use ambient air as the oxidizing agent.
This recent development follows an entire year over which the oil major had failed to mitigate the flaring at Liza-1, its very first field development in Guyana. Exxon was only meant to briefly flare gas at project start-up in late December last year, to test and fully commission the gas compression and injection systems at the site.
However, the company would end up flaring gas way longer than expected due to what it said to be a defective main and injection gas compressor.
According to an Environment Protection Agency (EPA) brief, ExxonMobil had said that the third stage-flash gas compressor and suction silencer had been sent for repair in Germany and were returned to the Liza Destiny FPSO in late October.
The EPA had said that same was being reinstalled and was expected to restart functioning in mid-November. Exxon, according to the November update, had expected the equipment to take one to two weeks of testing to confirm that the repairs and modifications worked.
Notably, at the end of October, the company had flared more than 16M cubic feet of natural gas, thereby making Guyana one of the top five countries in the world for volume flared per year, per capita. In September, Guyana had trailed Libya, Gabon, Oman, Qatar and Iraq, in total gas flared per capita, judging from statistics from the World Bank’s Global Gas Flaring Tracker Report (July, 2020). However, the increased flaring in October caused Guyana to surpass Iraq.
The company claimed it had to flare, since its gas compression equipment was defective and needed to undergo repairs overseas. The repairs reportedly proved difficult to undergo with haste, given limitations the COVID-19 pandemic safety guidelines have placed on companies. Exxon is yet to complete the repairs to all of its defective equipment.
Yesterday, Kaieteur News reached out to ExxonMobil’s Public and Government Affairs Advisor, Janelle Persaud, in seeking answers on whether the oil company’s gas compressor had been fully repaired, and on what date; what specifically was repaired on their defective equipment and at what cost, and on what date was the flaring had finally stopped.
Persaud failed on sharing specifics on the details requested by Kaieteur News. Instead, she sent a link to a video statement by Routledge, which mentioned no details to the company’s flaring.
Notably, EPA Head Sharifah Razack has promised to share with Kaieteur News details on Exxon’s updated details on flaring, today.
Subscribe to get the latest posts sent to your email.

Aug 29, 2026
Kaieteur Sports – The Limacol WCPL yesterday confirmed the overseas players who will represent franchises in the upcoming season, with a host of international stars from South Africa, Australia,...Aug 29, 2026
(Kaieteur News) – Christopher Ram is quite entitled to be unimpressed by the pace of the present Constitutional Reform Commission. In a recent letter, he compared the performance of the Carl Singh-led Commission with that of the 1999 Commission and concluded that the present body, after more...Aug 23, 2026
By Sir Ronald Sanders (Kaieteur News) – I have been an advocate of the Caribbean Court of Justice from its conception. In 2015, on the Court’s tenth anniversary, I described its creation as arguably the most significant institutional achievement of the English-speaking Caribbean since the...Aug 29, 2026
(Kaieteur News) – My position on Hon Minister of Public Works, Juan Edghill relative to the MV Barima tragedy is well known. Calls for his resignation or termination is mistaking a sardine for a shark. The tragedy is bigger than a minister (or two), bigger than the Cabinet. It reaches to...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com