Dear Editor;
With the talk about ending the operations and maintenance contract with Wartsila, and a sole-sourced Wind Farm with Mr Lloyd Singh, I ask: are we, GPL and the customers, being set up to be exploited?
The damage to the cable crossing the Demerara River (it is said by their own dredging contractor) must be considered a great failure at all levels of GPL. How did it happen? Everyone knows that there is an underwater cable and GPL knows exactly where it is and should have had sure methods of avoiding its damage.
Also, thinking of the number of days being taken to find a suspected fault on the five (5) kilometre line linking Kingston and Sophia one wonders whether GPL, including its Board, are not already stretched. There is word about other incidents being kept quiet.
That is why the talk of ending or changing the operations and maintenance contract with Wartsila seems ill advised at this time, when it doesn’t appear that the Board and Management of GPL are ready to take on additional load; nor can I imagine GPL ending the contract with Wartsila to hand it to any other.
Losses, both technical and commercial, have been the big problem of our electricity sector. A few years ago one IDB consultant produced and we published the losses for the geographical areas of some thirty feeders.
The great variation in commercial losses was brought before the public and I believed that keeping this focus with half-yearly determinations and publications of the information would put limits on what individuals inclined to stealing electricity would do or be allowed to do. I am very disappointed and consider it a great mistake that this programme has not been pursued.
With the IDB looking over our shoulders and differing with them any number of times over some twenty plus years, systems were developed for the good management of GPL.
One of the most important is the requirements and practice of submitting each year to the Minister and the Public Utilities Commission (PUC), the rolling five-year development and expansion (D&E) plan, with a fifteen-year perspective added later. The development of the Amaila Falls was our fifteen-year perspective.
The need for new, comparatively small Heavy Fuel Oil (HFO)- fuelled gen sets for new generating stations at Bartica and Anna Regina were evident and urgent. After our first discussions with Wartsila we wondered whether the small, 1.0 to 2.5 MW, units required had not fallen below Wartsila’s economic range and looked further afield to the 1 MW unit being installed (then) by RUSAL (they use the larger Wartsila units at other locations) and the 1 MW Hyundai unit at Banks DIH Thirst Park.
I contemplated a selected tender process, inviting Wartsila and at least these two others to bid for the gen sets (with auxiliaries) for new stations at Bartica and Anna Regina. We also contemplated that the next large station, five years or so further on, would be at the Canefield location (outside of New Amsterdam).
The fact is that except for studied and selected hydro sites (such as Amaila), renewable energy highly desirable as it is, and it is the energy of the future, is still generally today not directly competitive with fossil fuels.
The people of the developed countries, much richer than we, have been knowingly providing premium (higher) prices (which they could readily afford) for energy/electricity provided from renewable sources, so as to meet their commitments to lower their total and per capita carbon dioxide (CO2) production.
Our own Guyanese figures are so low, we are way below such requirements; there is no need and no economic justification for us preferring more overall expensive renewable energy; diesel units would have to be installed anyhow to back up the renewable energy sources of solar and wind.
Looking back now, there can be no doubt that the calls by the new Coalition Government for a green Bartica and a green Guyana were not fully informed and created confusion so that Bartica and Anna Regina (Essequibo Coast) have been suffering electricity outages of about twelve hours per day and there will likely be a fifteen-month delay in providing an economic, reliable supply of electricity. This evident misinformation and misjudgements of the Coalition Government deepen concern about whatever arrangements would be made with whomsoever for the Wind Farm at Hope Beach or elsewhere (or other renewable energy).
With our current income levels and where we are at in Guyana, lowest lifetime cost should prevail and apart from Amaila, diesel engines are difficult to beat (except in the hinterland and wherever homes are so far apart that the distribution cost is prohibitive). As everyone should recognize, solar and wind do not provide continuous, always-available power.
It is economic for GPL to pay only for the avoided fuel and maintenance costs discounted by the arrangements to offset/absorb the variations in the renewable energy supply.
With such an understanding we of the PPP/C kept our doors open to proposals for solar and wind generation and we would be looking to see that such principles are respected by our Coalition Government (if not, GPL consumers may well end up subsidizing the investors).
No doubt the generation-mix in the long term was something to start thinking about. For the record, on seeing a call from the Government of Japan for developing countries to apply for 1 to 3MW demonstration, utility-grade solar photo-voltaic (PV) plant we immediately applied, prepared and submitted a proposal, but along the way the Japanese Government suspended the programme pleading budget cuts.
Also, we kept on extending an MOU first entered into in the late 1990s or early 2000s for a Wind Farm at Hope Beach. In about 2014 Mr Lloyd Singh who had lately become a partner in the company, brought a particularly attractive proposal in which the Chinese Manufacturer was offering about 75% financing at a very low interest rate.
It began to appear that a Government guarantee of the loan might be required and shortly after we were told that that Chinese Manufacturer had withdrawn the offer. Mr Lloyd Singh brought another Chinese Manufacturer but it was much more expensive, unacceptably so.
We have some protection in that whatever the outcome of the Government’s sole-sourcing negotiations with Mr Lloyd Singh, the law requires the PUC to approve any Independent Power Producer (IPP) agreement which GPL intends to enter into.
Sam Hinds
Former President and Prime Minister.
Subscribe to get the latest posts sent to your email.
Rising Debt, Rising US Dollar Rate in Oil-rich Guyana!
Aug 05, 2026
Cricinfo – Pakistan pulled clear on an absorbing day of Test cricket that see-sawed one way and then the other. While West Indies had improved upon their position from 24 hours ago in the first...Aug 05, 2026
(Kaieteur News) – The sinking of the M.V. Barima has understandably produced anger, grief and frustration across Guyana, and in any functioning democracy a credible opposition would be expected to seize upon such a national tragedy and use it to hold the government accountable. That is what...Aug 02, 2026
By Sir Ronald Sanders (Kaieteur News) – Daniel Ortega has now said openly what his regime has demonstrated for years: the people of Nicaragua are not to be permitted to remove their rulers through elections. During celebrations marking the 47th anniversary of the Sandinista Revolution, Ortega...Jul 30, 2026
Hard Truths by GHK Lall (Kaieteur News) – A tragedy of catastrophic proportions is now Guyana’s to manage. An old passenger ferry boat went to the bottom. According to news reports of Saturday, 73 bodies have been recovered and 76 rescued. Taking the official count of 179 passengers on...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com