(Kaieteur News) – The Wales Gas-to-Energy (GTE) project is fast becoming a monument to mismanagement, mounting costs and the Government’s apparent reluctance to hold contractors accountable for repeated delays and escalating expenditure. What was sold to Guyanese as a transformative energy investment, promising cheaper electricity and relief for households and businesses, is increasingly looking like a financial burden with no clear end in sight.
The latest development is particularly troubling. Government is seeking another $24.7 billion (US$118 million) for the project, months after securing parliamentary approval for an additional $19 billion in July. The latest request, described as necessary to facilitate an expanded work programme, raises serious questions about the original project estimates, the contractor’s performance and the Government’s management of this critical national investment.
This newspaper reported that the Government had approved more than US$100 million in additional financing for Lindsayca, the contractor responsible for the project. Prime Minister Mark Phillips confirmed that additional financing was approved, although he could not immediately recall the exact amount. His assurance that the contractor received everything it requested is hardly reassuring to taxpayers who are being asked to finance the consequences of a project that continues to miss deadlines.
Even more disturbing is the US$97 million settlement that Guyana was forced to pay following a dispute with the Lindsayca/CH4 consortium. The Government also spent close to US$2 million on lawyers representing the country during the dispute. These are substantial sums of public money, yet the public has not received a sufficiently convincing explanation of how the country arrived at this position or what measures were taken to protect its financial interests.
The original contract was valued at US$759 million, with completion initially scheduled for the end of 2024. Here we are in November 2026, and the country is still being asked to find additional billions to keep the project moving. Worse, the Government’s revised commitment to have 57 megawatts of electricity available by December has become uncertain, with no definitive assurance from the responsible minister that the contractor remains on schedule.
This is unacceptable. A contractor cannot continually miss deadlines, demand additional financing and emerge from disputes with substantial settlements while the Government simply returns to the National Assembly for more money. There must be consequences when contractual obligations are not met. Public funds cannot be treated as an unlimited source of financing for poor project execution.
While Guyana waits for the promised electricity, it continues to spend heavily on alternative power generation. The cost of importing heavy fuel oil since 2024 is expected to reach at least US$619 million. Additionally, the country is paying approximately $126 million daily to rent two Turkish power ships to supplement the national grid.
These expenditures represent an enormous burden. They are costs that should have been reduced had the project been delivered within its original timeframe. Instead, Guyanese are left paying for fuel, rental power and an increasingly expensive infrastructure project that has yet to deliver the benefits promised.
And there is another dimension to this growing concern. The 220-kilometre pipeline constructed by ExxonMobil, which was completed in December 2024, is currently undergoing rehabilitation. ExxonMobil has not disclosed the cost of the ongoing repairs or provided the public with the price tag of the infrastructure. This adds another layer of uncertainty to a project whose overall financial implications are already becoming difficult to justify.
The Government has consistently promoted the GTE project as a major intervention that will reduce electricity bills by 50 per cent once fully operational. But promises of cheaper electricity cannot substitute for accountability, proper project management and transparency over expenditure.
The National Assembly must also exercise its responsibility beyond merely approving supplementary allocations. Every additional dollar requested should be subjected to rigorous scrutiny. Parliamentarians must demand detailed explanations of the expanded work programme, the additional financing approved for Lindsayca, the circumstances surrounding the US$97 million settlement and the contractor’s current obligations.
The public must also be told whether there are enforceable safeguards against further cost increases and what penalties, if any, apply when the contractor fails to meet agreed deadlines.
Guyana is fortunate to have substantial oil revenues, but that does not give any government the right to spend without adequate accountability. Oil money belongs to the people, and every expenditure must be justified by value, performance and results. The Wales GTE project was supposed to usher in a new era of affordable and reliable electricity. Instead, it is threatening to become a cautionary tale about what happens when ambitious national projects are allowed to proceed without sufficient transparency and effective oversight.
Subscribe to get the latest posts sent to your email.
Nov 21, 2026
(Kaieteur News) PARIKA — Pugnacious right-handed batter Kevon Boodie slammed a fiery, 60-ball 108 to spur Vergenoegen Kings to a comprehensive 120-run win over Hyde Park Sports Club last Sunday....Nov 20, 2026
(Kaieteur News) – Horse racing in Guyana has always been an exciting and popular sport. The horses run, the jockeys ride, the punters gamble and the owners hope. But there is one thing that seems to be moving at a considerably slower pace than everything else: regulation. Guyana finally got...Nov 01, 2026
By Sir Ronald Sanders (Kaieteur News) – When Commonwealth leaders gather in Antigua and Barbuda from 1st to 4th November, they should address a question that reaches beyond their association: how can countries of different size, wealth and outlook sustain cooperation in a world increasingly...Nov 21, 2026
(Kaieteur News) – Ever had old cars on their last gallon of gas, their last lines in the tires? I have. Ever been around a very sick streetwalker who demands a dime, then a dollar, then deliverance from the spirits that torment? It’s a case of in the pocket and out of the pocket. I...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com