Commuters travelling along the Linden-Soesdyke Highway will soon benefit from smoother and reduced travel time as construction on the critical road network nears completion.
The US$161M landmark project overall construction works now stand at approximately 90 per cent complete, according to Construction Manager at Namalco, Vishal Maharaj.
Speaking to the Department of Public Information (DPI) on Saturday, Maharaj said significant progress had been made across all major components of the project.
He explained that drainage infrastructure is also advancing steadily, with concrete drain construction around 70 per cent complete.
“We also have drainage works continuing. We have basket works to accompany the drainage and the different layers of paving taking place in conjunction. We are working simultaneously with each other,” he noted.
Maharaj noted that work is being carried out in sections to maximise efficiency while adapting to weather conditions.
“Based on the breaks in the weather, we are doing key works in various places to complete on time. We are trying to do our best with the continuation without compromising the quality of the works,” he said.
Despite periodic rainfall, the project remains ahead of schedule.
Electrical works have also commenced, marking another major milestone in the project.
Contractors have begun installing light pole pedestals and power boxes along the corridor.
Street lights are expected to be installed shortly. The contractor has already acquired 700 of the 1,300 street lights required. The remaining lights have been shipped and are expected to arrive in Guyana within a month and a half.
Meanwhile, the massive infrastructure project, once completed, will transform the Linden-Soesdyke Highway into a modern transport corridor capable of supporting increased traffic while improving safety and connectivity. It will also strengthen economic activity between the two regions.
The upgrade is being executed through a joint venture involving Trinidad-based Namalco Construction Services and local firm GuyAmerica Construction Inc.
The government has repeatedly urged contractors to complete the project ahead of its September 4 deadline. (DPI)
Subscribe to get the latest posts sent to your email.
Oct 16, 2026
…74-year-old captured three silver, one bronze at World Masters Powerlifting C/ships (Kaieteur News) – Guyana made an impressive start to the 2026 International Powerlifting Federation (IPF)...Oct 16, 2026
(Kaieteur News) – It is said that one should not speak ill of the dead. But there is something about the tributes paid to deceased persons that encourages the living to improve the reputation of the dead. At the recent evening of reflection for Robert Corbin, Bharrat Jagdeo appeared to have...Oct 11, 2026
By Sir Ronald Sanders (Kaieteur News) – Who speaks for Haiti? It is a question the international community can no longer avoid. For years, governments and international organisations have insisted that the country’s deepening crisis must have a “Haitian-led solution”. The principle is...Oct 16, 2026
(Kaieteur News) – It is the Guyana Way. The law provides. The numbers spiral. The wait intensifies. The suspense pierces. Sounds like a PPP Govt production. It is. On standby with hand outstretched are 27,000 Guyanese. They have given their labours to Guyana. They are NIS...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com