Facing increasing public criticisms, the Guyana Power and Light Incorporated (GPL Inc.)
yesterday admitted that it barely has enough power to meet peak demands.
As a matter of fact, any engine that goes down will lead to load shedding.
Daily, residents have been complaining of outages with little explanations from GPL. The state-owned power company, in a statement, said that efforts are progressing to restore generation capacity to mitigate the occurrence of service interruptions in the Demerara-Berbice Interconnected System (DBIS).
“The current available generation capacity is 116 megawatts with a peak demand (between 18:30hrs and 22:00 hrs) of approximately 110 megawatts. Whilst the available capacity may appear adequate to meet demand; it leaves insufficient reserve capacity to cater for unexpected and additional loss of generation,” the statement said.
The company said that in instances of insufficient available generation capacity to meet the demand, customers in various areas within the DBIS may experience an interruption in the supply of electricity.
“It is important that the company states very clearly that, this current generation challenge is temporary whilst two generation units with an aggregate generation capacity of 13.8 megawatts are offline for maintenance and are expected to become operational shortly.”
GPL said it remains cognizant of the inconveniences these interruptions cause.
“…We wish to reassure customers that we remain resolute in restoring a stable supply of electricity and extend sincerest apologies to our valued customers.”
GPL is exploring tapping into natural gas and has announced plans that include a 50 megawatt power plant to tap into that. A number of solar plants are also being considered.
The Government of Guyana last year took a decision to release Finnish Company, Wartsila, of its management contract of several engines in the Demerara and Essequibo area.
A new company was formed- Power Producer and Distribution Incorporated (PPDI) – which took over the local staffers of Wartsila. They are managing the engines.
Subscribe to get the latest posts sent to your email.
Comments are closed.

Sep 26, 2026
Cricinfo – West Indies’ players are set to endure a pay cut, with Cricket West Indies (CWI) announcing a 25% reduction in retainer fees as part of a wide-ranging series of steps being...Sep 26, 2026
(Kaieteur News) – There are times when professional rivalry becomes a luxury and solidarity becomes a duty. Washington has just provided one. The Trump administration has barred CNN, MS NOW and Politico from the White House, accusing them of publishing what President Donald Trump calls “fake...Sep 20, 2026
By Sir Ronald Sanders (Kaieteur News) – Crime in Latin America and the Caribbean is no longer only a matter for the police. It is weakening societies, draining economies and obstructing development. It is also testing public confidence in courts, governments and democratic institutions. The...Sep 25, 2026
(Kaieteur News) – If President Irfaan Ali and Vice President Bharrat Jagdeo are truly serious about contract renegotiations, they have an ace. It’s Guyana’s China card. China wants something. Exxon (America) wants something. Guyana wants something. I repeat if the Ali-Jagdeo led PPP Govt...Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: glennlall2000@gmail.com / kaieteurnews@yahoo.com
Guyana get oil gold diamond and you can’t even generate 115 megawatts of electricity.Buy equipment or beg for help Generations now and we still using bottle lamps in our beautiful city of Georgetown Guyana. You have to start generating 300 megawatts so when the time come for 4 you already have 5. One step ahead. You need to pay for these advice