Latest update December 17th, 2024 3:32 AM
Jul 23, 2024 News
Kaieteur News – The $35M sanitation and water supply networks project in Kwakwani, Region 10 are progressing well, the Guyana Water Incorporated (GWI) said on Monday.
“With regards to sanitation, the (Caribbean Regional Fund for Wastewater Management+ Guyana Project) CReW project is almost 75% completed in Kwakwani with activities such as the clearing of blockages in the more than 70-year-old sewerage network, upgrades to damaged chambers, repairs and/or construction of seven septic tanks and adding of tertiary treatment to remove pathogens and nutrients from the waste,” the water company said in a press release.
The GWI said that it is advancing interventions to ensure better water distribution and sanitation systems in Kwakwani, where more than 7000 persons would benefit from the improved services.
GWI’s Chief Executive Officer (CEO) Shaik Baksh led a technical team on a site assessment in the community over the weekend where he inspected the water treatment plant and storage facilities and held discussions with the Kwakwani Utilities Incorporated (KUI).
The team also visited several areas where GWI is leading infrastructural upgrades to the sanitation network as part of the Caribbean Regional Fund for Wastewater Management+ Guyana Project (CReW+). ApproximatelyGY$35 million is being invested in Kwakwani under this project.
KUI, a subsidiary of the National Industrial and Commercial Investments Limited, is responsible for managing Kwakwani’s main utility services including water and sanitation. KUI’s General Manager Winston Rozario and staff updated the GWI personnel on challenges with water supply and distribution including blockages in the system that contribute to low water levels in some areas. Currently, water is supplied to residents for three hours in the morning and another three during the afternoon. KUI requested GWI’s support to improve these services.
Mr. Baksh noted his satisfaction with the existing water treatment and storage system, the environmental upkeep of the facilities and the existence of a good water source, which are key for continued service. He assured that GWI, based on its evaluation, will develop an improvement programme to support Kwakwani’s water quality and supply.
However, Mr. Baksh emphasized the need for data on the distribution network so GWI’s technical personnel can comprehensively evaluate the needs and identify solutions. Data is required on production, storage and consumption. The GWI and KUI teams agreed that there is need for greater public awareness on water conservation and storage especially since the community is supplied with non-revenue water.
Additionally, the project will support the community’s secondary school to upgrade its waste-to-energy facility enabling the students to continue using pig manure to produce cooking gas for their home economics classes. The project is awarded to local contractor, Sachia Jones Construction and Supplies Services of Kwakwani.
Dec 17, 2024
SportsMax – West Indies white ball Head Coach Daren Sammy will also take over the role as head Coach of all West Indies Men’s senior teams as at April 1, 2025, Cricket West Indies (CWI)...Peeping Tom… Kaieteur News- According to MSNBC’s Rachel Maddow in her book, Blowout: “The oil and gas industry... more
By Sir Ronald Sanders Kaieteur News – The government of Nicolás Maduro in Venezuela has steadfast support from many... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]