Apr 05, 2017 News
GreenHeartTree Energy (GHTE) has taken the initiative to design, engineer, procure,
construct and deliver a non-grid connected solar PV micro-grid system for the Paramakatoi Flavours Sun-Dried Tomato Plant. This system takes into consideration the actual climatic data and historical weather patterns of the area.
Engineers ran multiple simulations to determine the correct system size based on battery storage capacity, solar PV capacity and the predicted electrical loads requested in the Request For Proposal (RFP) by the Institute of Applied Science and Technology (IAST).
The Paramakatoi Flavours system includes three solar PV racks or arrays complete with top grade Hanwha Q-Cell Modules and American made, German Engineered Schletter Racks. Adjacent to the solar PV arrays is a small building, shipped from Canada, designed to house the batteries and electronics.
The lead-acid batteries are on a pre-assembled custom built battery skid. Each battery comes complete with a visual monitoring float for each cell within every battery. GHTE has included in the shipment additional battery water to ensure the system is maintained using the correct materials and fluids.
The battery inverter, solar PV inverter and a Smart-Transformer will be mounted inside the building on a custom build galvanized steel frame.
AC Coupled MircoGrid System
GHTE has engineered a system that is on the leading edge of technology for microgrid systems. This is an AC coupled system unlike a typical DC coupled one. Even though they usually include an inverter, most battery-based PV systems are “DC-coupled”
AC coupled PV systems are gaining wider support through several battery-based inverter manufacturers.
GHTE pre-assembled the entire battery system on a custom built skid and electronic components on a custom steel frame to test and confirm operation prior to shipping. Testing in Canada ensures that when the system arrives in Guyana the ‘bugs’ have been worked out and reduces the installation time on site.
Once the system installation is complete engineers complete a final quality control check to ensure that all check points of the system construction have been completed to our high quality standards.
GHTE has provided technical manuals for all components used along with a technical user’s guide that outlines necessary maintenance check-points, schedules and defined user necessary operating details.
Feb 04, 2025
Kaieteur Sports- The Kaieteur Attack Racing Cycle Club (KARCC) hosted the 6th edition of its Cross-Country Cycling Group Ride, which commenced last Thursday in front of the Sheriff Medical Centre on...Peeping Tom… Kaieteur News- In recent days there have been serious assertions made and associations implied without... more
Antiguan Barbudan Ambassador to the United States, Sir Ronald Sanders By Sir Ronald Sanders Kaieteur News- The upcoming election... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]