Sep 14, 2013 News
An Australian outfit, which has concessions in Region Seven, is now moving to build a large scale gold mining operation.
According to the Government regulator, Environmental Protection Agency (EPA), in a notice to the public yesterday published in Kaieteur News, Pharsalus Gold Inc. has submitted an application to EPA for an environmental authorization to undertake the mining project within the Hicks/Kaburi Concession situated at Black Water Creek, Kaburi Area, Region 7.
“This project would entail the development of an open pit mine that involves, clearing of vegetation, removal of topsoil and blasting of hard rock, construction of: processing facility, laboratory, cyanidation facility, power generating facilities and ground water wells. It would also include upgrading of an existing access road,” the
notice said.
According to EPA, according to regulations, an Environmental Impact Assessment (EIA) is required before any decision to approve or reject the proposed project is taken, since the development may have significant impacts on the environment.
EPA said that members of the public have 28 days to make written submissions to the agency, raising questions which they want answered in the EIA.
Pharsalus Gold Inc. is a wholly-owned subsidiary of Australia-based Azimuth Resources Limited.
The company, in areas known as Smarts and Hicks, part of an 1100 kilometer square concession, was acquired by vendor agreements and direct grants to Pharsalus Gold Inc., a wholly owned subsidiary of Azimuth Resources Limited, according to information published on EPA.
It is intended that Pharsalus will operate an open cut mine, processing plant, tailings storage facility, mine site accommodation and additional infrastructure required to recover and to process ore for the recovery of gold.
Development and operation of the mine site will be done in several phases with power for mine site operations provided by nine one-megawatt diesel generator sets.
Pharsalus said that the mine site will be serviced by road and air with a new access road to connect the mine site to the Amaila Falls Hydropower service road.
A permanent airstrip will be constructed also. It will be constructed along with security and a terminal building.
The ore exploitation rate will result in a mine life of 15 years or more depending on the final processing rate.
The process plant will have a nominal capacity of an estimated 600,000 tonnes to 750,000 tonnes of ore per annum, designed to produce up to 110,000 ounces of gold per annum based on an average overall recovery of 92 per cent.
Apr 07, 2025
-PC, West Ruimveldt and Three Mile added to the cast Kaieteur News- Action returned to the Ministry of Education (MoE) ground in Georgetown as the Milo/Massy Under-18 Football Championship determined...Peeping Tom… Kaieteur News- The Vice President of Guyana, ever the sagacious observer of the inevitable, has reassured... more
By Sir Ronald Sanders Kaieteur News- Recent media stories have suggested that King Charles III could “invite” the United... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]