Dear Editor:
Please allow me to respond to the article “Amaila Falls Hydro – A disaster in the making” which was written by Mr. Christopher Ram and published in the Stabroek News of March 29, 2013.
Mr. Ram continues on his campaign to denigrate the Government of Guyana by attempting to intensify the true costs of constructing the Amaila Falls Hydro Project. He is grasping at straws in his endeavour to attribute all sorts of additional costs to the project based purely on speculation.
Mr. Ram lacks a sense of objectivity in his analysis, since what he has done was to nitpick selectively his source of information to arrive at his cost of construction of a 165 MW station at US$320 to US$360 million. This works out to be an average of US$1.9 to US$2.2 per Watt, which is at the lower end of the cost of constructing this type of plant with existing infrastructure.
A more realistic cost to construct a new hydroelectric plant is US$5 per Watt and a 165 MW plant works out to be US$825 million. This realistic estimate is US$15 million less than the proposed construction cost of the Amaila Falls Hydro Project, which is US$840M. However, the cost of construction varies depending on location.
In the case of the location identified for the Amaila Falls Hydro Project, this requires a significant investment in infrastructure development works to access the site. An example of how vastly the cost for this type of plant varies, based on a study conducted in 2007 in Canada by Hydro Review is explained below.
The November 1, 2007 issue of Hydro Review states that Canada was pursuing more than 25 new Hydro projects totalling more than 2,500 MW at a cost of more than US$15.6 billion. That is equivalent to US$6.24 per Watt and based on inflation and compounding over 5 years the cost would be US$6.81 per Watt. Thus if started today, the cost would be more than US$17.025 billion. Extrapolating those values, the 165 MW Amaila Falls Hydro Project should cost US$1.123 billion.
Hydro Review examined 15 Hydro Projects across various Provinces in Canada. The complexity of some of the projects allowed for only 10 to be summarized in the accompanying table:
Plant | Location | Generating Capacity – MW | Construction Cost_- US $M |
Ashlu Creek Hydro Project | Ashlu Creek, British Columbia | 49 | 125 |
Brilliant Expansion | Kootenay River British Columbia | 120 | 205 |
Chute-Allard and Rapides-des-Couers | Saint-Maurice River Quebec | 138 | 680 |
Eastmain-1-A and Rupert Division including La Sarcelle | Rupert River Quebec | 768 | 5000 |
East Toba River and Montrose Creek | East Toba River, British Columbia | 196 | 650 |
McLeod Dam Green Energy Project | Moira River, Ontario | 0.95 | 4 |
Mercier | Gatineau River, Quebec | 50.5 | 140 |
Peribonka
|
Peribonka River, Quebec | 385 | 1200 |
Umbata Falls Hydro Electric Project | White River Ontario | 23 | 60 |
Wuskwatim Generating Station | Burntwood River Manitoba | 200 | 1300 |
Total | 1,930.45 | 9,364 |
While the costs vary from a low of US$1.7 with existing infrastructure to a high of US$6.5 per Watt for new plants across the different projects within Canada, the average construction cost based on 2007-dollar value is $4.8 per Watt. This offers an objective look of how the cost can vary depending on a number of contributing factors.
I do not have the space to get into the details here. Suffice to say that the matrix provides some amount of details and a calculator can be used to work out the average cost.
Canada is a highly developed country with one of the strongest economies in recent times. It has a variety of highly developed transport infrastructure, thus ensuring easy access to the various locations. The Amaila Falls Hydro Project is a first for Guyana in terms of construction and production of power generation operation of this magnitude and is being done in the remote parts of Guyana, where the road network infrastructure is mostly at a primary stage or non-existent. Guyana has the potential to produce over 5000 MW of Hydroelectric power and the Amaila Falls Hydro Project is a stepping-stone to becoming energy independent.
Mr Ram further compared the cost of a hydrocarbon-powered plant at US$1. per Watt, but failed to mention that the run life costs as well as the maintenance costs are far greater than the installation cost of a hydrocarbon powered plant. I agree that the accrued interest will inflate the construction cost, but maintenance of a renewable sourced energy is far less than that of a similar size hydrocarbon powered plant.
Guyana, through the Government of Guyana has embarked on a program to develop its renewable sources of energy to attain energy independence. This also enhances our concern for the environment for which we already have attained global acclamation (LCDS). The Amaila Falls Hydro Project offers much more benefits in terms of developing our manufacturing sector and opens up the possibility of a light-rail overland means of transportation to access the interior locations in the future.
Mr. Ram seems to be more inclined to remain in the current rut of relying on the hydrocarbon powered plants, where we put ourselves at risk by depending on oil and being saddled with a huge oil bill. This is wrong. Mr. Ram has been wrong before when he was discussing the PPP/Civic Manifesto in Stabroek News dated October 26, 2011 in an article titled “A mixture of distortions, untruths and misrepresentations”.
In the case of the one laptop per family project, Mr. Ram commented that the Lenovo computer technology was not tested. I wish to state that Lenovo actually bought the computer division of IBM in 2005. The IBM computer technology is definitely tested and proven. Lenovo is simply a new brand name appended to the IBM computer technology.
I find it extremely disappointing when people try to score cheap political points by merely speculating and not conducting the requisite research on the subject, they want to discuss. It reflects a sad lack of patriotism when persons attempt to hold back the march of progress and a better future. Mr. Ram seems bent on misleading the Guyanese public by exacerbating the facts in his vile attempts to discredit the Government of Guyana in its pursuit of projects that will enrich the lives of Guyanese.
David Gopaul
Jan 31, 2025
2025 CWI Regional 4-Day Championships Round 1…GHE vs. BP Day 2 at Providence -Champs trail by 31 runs heading into Day 3 Kaieteur Sports- Cracking half-centuries from new Guyana Harpy Eagles...Peeping Tom… Kaieteur News- The government through its superior management of the economy says that it has bestowed... more
Antiguan Barbudan Ambassador to the United States, Sir Ronald Sanders By Sir Ronald Sanders Kaieteur News- The upcoming election... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]