Major works will soon commence on the East Coast of Demerara as bids have been accepted for the upgrade of the four-lane road from Better Hope (Lot 1) to Montrose to La Bonne Intention (lot 2).
Already the four-lane road exists from Vlissengen Road to Better Hope. Some five (5) local companies yesterday submitted their bids for the project, with the engineer’s estimate for the project totaling some $620,520,167 for Lot 1 and $851,140,622 for Lot 2.
Bidder | Amount |
Syms General Contractor Inc. | Lot 1.$610,649,220
Lot 2—————— |
Geico Construction | Lot 1.$573,384,967
Lot 2.$864,940,576 |
Falcon Transportation | Lot 1.$463714,760
Lot 2.—————- |
Dipcon Engineering | Lot 1.$498,812,318
Lot 2.$671,623,054 |
BK International | Lot 1.$531,351,450
Lot 2.$704,750,820 |
There were three (3) bids for the supply of materials and labour-drilling potable wells at Skeldon, Region 6. The Engineer’s Estimate: $91,230,010
Bidder | Amount |
S. Jaghmohan Hardware Supplies | $95,741,780 |
BK International | $91,838,408 |
Nabi Construction | $96,955,010 |
Nine (9) bids were submitted for the construction of an Artificial Insemination Laboratory at Mon Repos. The Engineer’s estimate: $31,532,855.
Bidder | Amount |
G. Bovell Construction Services | $30,858,889 |
Parnance Nandalall | $25,464,467 |
Linton Mickle Enterprise | $36,882,913 |
S. Khan General Contracting | $35,448,343 |
Nabi Construction Inc. | $34,008,481 |
Alvin Charalmuttoo Construction | $27,698,652 |
Yogeshwar Bhola Contracting Services | $27,470,583 |
Pioneer General Construction | $31,003,096 |
Horizon Electrical & General Construction | $29,667,271 |
With an engineer’s estimate of $152,640,452 there were four (4) bids for the rehabilitation of the Ministry of Home Affairs building
Bidder | Amount |
Pioneer General Construction | $143,413,867 |
Horizon Electrical | $149,992,445 |
Nabi Construction | $155,061,653 |
R. Bassoo & Sons Construction | $144,969,433 |
And five (5) bids were submitted for the reconstruction of the Kaburi Village Road. The Engineer’s estimate is $59,360,500
Bidder | Amount |
Rookhan Ramotar | $90,235,500 |
Mekdeci Machinery & Construction | $58,781,250 |
Tulsi Persaud Quarry | $54,348,000 |
H N Pasha General Building | $57,260,00 |
Murice Balgobin | $49,863,750 |
Apr 05, 2025
2025 CWI Regional 4-Day Championships Round 6… – Eagles lead by 239 runs heading into last day Kaieteur Sports- In-form batsmen, Kevlon Anderson and Captain Tevin Imlach played similar...Peeping Tom… Kaieteur News- There exists, tucked away on the margin of maps and minds, a country that has perfected... more
By Sir Ronald Sanders Kaieteur News- Recent media stories have suggested that King Charles III could “invite” the United... more
Freedom of speech is our core value at Kaieteur News. If the letter/e-mail you sent was not published, and you believe that its contents were not libellous, let us know, please contact us by phone or email.
Feel free to send us your comments and/or criticisms.
Contact: 624-6456; 225-8452; 225-8458; 225-8463; 225-8465; 225-8473 or 225-8491.
Or by Email: [email protected] / [email protected]